Project
|
Members
|
Date
|
Time
|
Block - 1
|
08-112,113,125,156,161,
09-101, 09-110
|
21-Nov-11
|
10AM - 12.30PM
|
Block - 2
|
08-106,115,120, 121,
151,160, 09-109
|
1.30PM - 4.00PM
|
|
Block - 3
|
08-118,122,134,140,163,
09-103,111, 106
|
22-Nov-11
|
10AM - 12.30PM
|
Block - 4
|
08-124,131,135,138,165,
09-117
|
1.30PM - 4.00PM
|
|
Block - 5
|
08-126,129,139,145,
147, 149,155, 09-102, 115
|
23-Nov-11
|
10AM - 12.30PM
|
Block - 6
|
08-102,105,117,133,141,143,
09-105, 107,
|
1.30PM - 4.00PM
|
|
Block - 7
|
08-137,152,153,154,
158, 09-104,112
|
24-Nov-11
|
10AM - 12.30PM
|
Block - 8
|
08-101,103,109,114,144,162,
|
1.30PM - 4.00PM
|
|
Block - 9
|
08-104,109,128, 09-113,114
|
25-Nov-11
|
10AM - 12.30PM
|
Block - A
|
08-127,136,146,150, 09-108,116
|
1.30PM - 4.00PM
|
- Student should submit Project work along with Drawings, BOQ, BBS, Material Requirement Statements
- Power Point Presentation - Scope of work, Area of Study, Maps, Summary of data, and Conclusion
- Viva Voce
List of Drawings for Mini Project:
|
|||
1
|
Location Map
|
||
2
|
Block Map
|
||
3
|
Architectural Drawings (all floors)
|
||
4
|
Structural Drawings
|
||
a. Centerline
|
|||
b. Footings
|
|||
c. Columns
|
|||
d. Plinth Beam
|
|||
e. Slab
|
|||
f. Roof Beams
|
|||
g. Staircase
|
|||
h. Brickwork
|
|||
5
|
Retaining wall
|
||
a. RR Masonary (Plan & Section|)
|
|||
b. RCC (Plan & Section)
|